Worked example
The Cash Gap on a Contract: Payment Lag Plus Retainage
Contractors run out of cash on profitable jobs because costs go out before payments come in. Example: a six-month, $1,200,000 subcontract billed at $200,000 a month, with 10% retainage held until closeout and payment about 45 days after each bill. Job costs run 85% of billings ($170,000 a month), paid as incurred. Assumptions for illustration only — your contract sets the retainage and payment terms.
Amount
Monthly costs you pay
$170,000
Monthly billing / collected after 10% retainage
$200,000 / $180,000
Costs out while you wait about 45 days for payment
about $255,000
Retainage held by the end of the job (10% × $1,200,000)
$120,000
Peak cash you must carry, near the end
about $375,000
That peak is what a line of credit should cover — and why lenders ask for your work-in-progress schedule and accounts-receivable aging, not just tax returns. The retainage comes back only at closeout, sometimes months later, so count it as tied up. Factoring an invoice can bridge one slow payer, but it is priced per 30 days and costs far more than a line used the same way.
FAQ
Construction Business Loan FAQs
Common questions about contractor financing
What loans are available for construction companies?
Equipment financing and invoice factoring are the most-used by contractors.
How big a line of credit does a contractor need?
Size it to the peak cash a job ties up: costs paid while you wait for payment, plus retainage held until closeout. On a six-month, $1,200,000 job billed monthly with 45-day payment and 10% retainage, that peak is roughly $375,000 near the end of the job. Lenders will ask for your work-in-progress schedule and receivables aging.
How does invoice factoring work for contractors?
Factoring lets you sell unpaid invoices to a factoring company for 85–95% of face value upfront. The factor collects from your client (GC or government agency) and remits the balance minus a 1–5% fee. No debt is added to your balance sheet. Approval is based on your client's credit, not yours.
Can a construction company get an equipment loan?
Yes. Equipment financing is one of the fastest options for contractors. Approval in 1–5 days, 600+ credit accepted, and the equipment serves as collateral. Most lenders finance 80–100% of equipment cost at 6.5–20% APR for 2–7 years.
What credit score is needed for a contractor loan?
Equipment financing and invoice factoring are accessible at 600+ and 500+ respectively. SBA loans require 680+. Lines of credit need 650+. If your personal credit is below 620, prioritize invoice factoring or equipment financing while rebuilding your score.
How can contractors cover payroll between draws?
A business line of credit (8.75–45% APR) or invoice factoring are the best options. Set up a line of credit before you need it — lenders prefer approving credit lines to businesses not in crisis mode.
What is a construction bridge loan?
Bridge loans provide short-term capital (6–36 months) to cover gaps between project phases or pre-construction expenses before permanent financing. Rates run 6.25–13% APR. They require a clear exit strategy such as a construction-to-permanent refinance.